Timetable

This is an indicative timetable. Please note dates are not confirmed and can be subject to change.

2014

Quarter one (Jan-Mar) Tendering of Balance of Plant contract
Quarter two (Apr-Jun) Commence construction works on site with site establishment and commencement of road and foundation construction
Quarter three (Jul-Sep) Ongoing work on onsite roads, foundations and switchgear building
Quarter four (Sep-Dec) Ongoing work on onsite roads, foundations and switchgear building

2015

Quarter one (Jan-Mar) Ongoing work on onsite roads, foundations and switchgear building and commencement of cable installation
Quarter two (Apr-Jun) Completion of the civil and electrical works on site and commencement of site restoration and landscaping
Quarter three (Jul-Sep)

First turbine to arrive (Jun/Jul)

Completion of site restoration

Quarter four (Sep-Dec)

Grid available for export of electricity (Nov)

Final turbine to arrive (Dec)

Commence commissioning of the site (Nov/Dec)

2016

Quarter one (Jan-Mar) Ongoing commissioning of the site
Quarter two (Apr-Jun) Wind farm fully operational and works complete (Apr)

It is anticipated that the wind farm will be fully operational by early 2016.