02 March 2014

Traffic updates for Sevor Farm Solar


Friday 14 February 2014

Around 80 percent of the deliveries have been made to site, for instance only 8000 of the 40,000 solar modules are still awaiting delivery. We anticipate that deliveries will continue to site until the end of this month (up to 15 lorries a day).

Thursday 13 February 2014

There will continue to be 15 lorries per day (Mon-Fri) arriving to the Sevor Farm Solar site, with an additional two lorries on 21st February, 24th February and 25th February.
  

Monday 03 February 2014

Monday to Friday of this week there will be approximately 15 lorries per day driving to site.

We would like to apologise for any inconvenience caused during this time.